Pregnant leach solution being processed at Xincheng's pilot cell

From Ore To Cathode

Our modular leaching, solvent extraction and electrowinning process is designed to turn Zambian copper into LME-registrable cathode — commissioning April 2026, in production that June.

3
Modular SX–EW plant units
30MT
Cathode capacity per month
$5M
Full scale-up capex plan
100%
Permits & licenses secured
The Process

Copper leaching, solvent extraction & electrowinning

Each modular plant takes copper through four stages, converting run-of-mine material into finished cathode ready for the market.

01

Sourcing & Crushing

Copper ore is sourced from Zambian deposits and reduced in size ahead of leaching. Once our concentrator plant investment is complete, this stage will include flotation, gravity separation and crushing on our own equipment.

02

Leaching

Crushed material is leached to bring copper into solution, producing a pregnant leach solution (PLS) rich in dissolved copper.

03

Solvent Extraction (SX)

The pregnant leach solution is purified and concentrated through solvent extraction, isolating copper from impurities before it reaches the electrowinning cells.

04

Electrowinning (EW)

An electric current plates high-purity copper onto starter cathodes inside the electrowinning cell, building finished copper cathode sheets ready for stripping, weighing and dispatch.

Freshly stripped copper cathode starter sheet
Today’s Operations

Producing concentrate while we scale to cathode

While our modular SX–EW plants are commissioned, Xincheng already produces copper concentrate through tolling agreements for export to China, and trades zinc ore, copper ore and manganese ore into the regional market.

This gives customers continuity of supply today, with a clear, funded pathway to in-house cathode production from June 2026.

Roadmap

2026 commissioning timeline

Complete

Permits & Licenses

All permits and licenses required for production are in place.

Ongoing

Concentrate & Ore Trading

Copper concentrate tolling for export to China; trading zinc, copper and manganese ore.

April 2026

Plant Commissioning

Commissioning of three modular copper leaching & SX–EW plants.

June 2026

Cathode Production Begins

Copper cathode production starts at 30MT per month capacity.

Scaling The Value Chain

Where the next investment goes

A $5,000,000 capex plan takes Xincheng from ore trader to fully integrated copper producer.

$2,500,000

Mining Equipment & Machinery

Expanding our own extraction capability at source.

$1,500,000

Flotation, Gravity & Crushing Plant

A dedicated concentrator converting copper ore to copper concentrate.

$1,000,000

Cathode Production Modular Units

Additional modular copper leaching & solvent plant capacity.

Traffic & Logistics

Warehousing, storage & delivery

Our traffic function keeps material moving — from receiving through to the customer interface.

Receiving

Incoming ore and concentrate logged and quality-checked on arrival.

Storage & Warehousing

Covered and open stockpiling suited to each commodity.

Materials Management

Supplier management and inventory control across all trading lines.

Delivery

Ex-warehouse dispatch through to the customer interface.

See It For Yourself

Want a closer look at our plants and process?

We welcome site visits and due-diligence discussions with serious buyers and partners.